KLM Module 001-010: Testing on going using USB. We have 4 test stations running concurrently.
Slow testing since USB is slow. UH POcket DAQ has stability issues which we are working with KEK to fix.
We are testing KLM module 001-010. The daughtercards with problems have been reworked locally here in Hawaii.
9:10 AM
→
9:25 AM
TOP Testing: Module 01 FW15m
9:25 AM
→
9:35 AM
TOP KEK: Debugging10m
Slides
Hawaii to make a log and post the parts used in each module assembly.
9:35 AM
→
9:40 AM
TOP HW: Carriers, laser, SC5m
Slides
Chris: do not stick the test board too hard into the test station, the pogo pins are only to be pressed 50% not more.
If they are presses fully, there is a chance they will get stuck into the sleeve.
9:40 AM
→
9:50 AM
TOP HW: SCRODs, Pittsburgh10m
Slides
9:50 AM
→
9:55 AM
TOP FW: feature extraction, belle2link and overall5m
Produced a list of tasks w remaining requirements ofr the FW, which is in progress.
B2L seems to be working now.
HSLB FW that used the onboard clock worked fine everywhere.
get rid of PLLS. clock needs to go through dedicated route. routing ref clock through fabric makes is suseptible to small supply voltage variations which will add jitter.