6-Aug-2015 US Belle II HW/FW Meeting

Pacific/Honolulu
Tentative agenda:

1) Brief KLM hupdate
2) Detailed discussion on FW work for module 01 testing
3) travel plans related to 2

There are minutes attached to this event. Show them.
    • 1
      KLM: HW, FW, TargetX Tests, open issues
      SCROD Rev A+MB HW should be here in Hawaii next week.
      Daughtercards arrive week of AUg 24 and testing will start immediately for all ~150 modules.

      Ehut has just been powered up, Isar to test functionality and possibly take data.

      Isar to create and send out a document on concurrent readout of scintillator and RPC (consult Brandon on this)

      It has been unclear if gas was flowing at the time of data taking prior to shutdown. The gas will not flow for another 2 weeks after power up which will be about ~8/20/2015.

      Leo to send out a doodle poll for a dedicated KLM CRT meeting where people from Japan, Hawaii and IU/east coast can potentially attend.

      Things like HV cables, fiber trunks purchasing still needs to be discussed.

      The last data taken is located at:
      ccw04.cc.kek.jp:/home/belle2/isar/public
      150724_KEK_KLM_CRT_001_root_output.zip    (~1e6 events of single sector scintillator and RPC)
      150725_KEK_KLM_CRT_002_root_output.zip    (~500k events if single sector scintillator and RPC)
      150730_qt2_HV_71p0_HSLBad_1kevts_root_output.sroot  (~1k events of two almost front facing sectors: two HSLBs a and d concurrently- data taking stops after ~1k events- debug in process)

      Parsed data is located at:
      ccw04.cc.kek.jp:/gpfs/home/belle/vossen/cosmicData

    • 2
      TOP Testing: Module 01 FW
      Slides
    • 3
      TOP KEK: Debugging
    • 4
      TOP HW: Carriers, laser, SC
    • 5
      TOP HW: SCRODs, Pittsburgh
    • 6
      TOP FW: feature extraction, belle2link and overall